Apollo Tyres engaged Shah & Talati for the expansion of their Bias plant in 1996. This was a brownfield expansion and we have been associated with Apollo since then. Shah & Talati has designed the following expansions / additions at Waghodia Facility

  1. Expansion in Bias Plant – 1996-1998,
  2. Finished Goods Store – 2003-2004
  3. 5 MW Captive Power plant – 2004-2005
  4. Banbury Addition – 2004-2005
  5. RMS and FGS store Expansion – 2007-2008
  6. Radial tyre plant expansion and a new OTR facility for Apollo tyres – 2008-2009
  7. 190” Press addition – 2010-2011

 

SCOPE:

Architectural, Structural, Contract Management, Site supervision

Waghodia
Year 1996 to Present